Vicuña, the joint venture of BHP and Lundin Mining, awarded sections E and F of the Northern Corridor, the access road to the Vicuña Project in San Juan province, to a joint venture (UTE) formed by San Juan-based Minera Zlato and José J. Chediack: 50 km of high-mountain road between La Majadita and the Vicuña Camp, with rock blasting and slope stabilization, the company reported. Before making the award, Vicuña ran a new competitive process among prequalified companies.
Section E covers 20 km to La Brea and reaches 4,410 meters above sea level, with a 70-meter right-of-way. The work includes clearing and preparing the ground, excavation, cut and fill, subgrade and base course, culverts, piers and signage.
Section F adds 30 km to the camp and, according to Vicuña, poses the greatest construction challenges because of the area's geography. It involves drilling and blasting, slope stabilization and channelization of watercourses, as well as runaway truck ramps, waterproofed trenches, gabions, reinforced embankment walls, backing-type barriers and stabilizing mesh.
In January, Vicuña had identified the UTE of Terusi Construcciones and Semisa Infraestructura as the contractor awarded sections E and F in April 2025.
Work on both sections had begun in 2025 and was halted in April 2026 for the winter operations period in the Andes. The company said it is resuming execution and aims to make progress before the 2027 winter.
Vicuña Contracts the Corridor Section by Section
Vicuña describes the Northern Corridor as a route of about 220 km. In its January announcement, the company detailed sections A through D, which exceed 170 km. Section A, comprising subsections A1 and A2, covers 63.6 km from Angualasto to Junta La Palca and includes a 100-meter bridge over the Blanco River at Piedras Pintadas. Sections B, C and D link Junta La Palca with La Majadita, with about 107.4 km of construction involving large-scale earthworks, civil structures, drainage and containment systems.
Subsections A1 and A2 went in September to the UTE of Contreras, BBC and Construmin. According to Vicuña, that partnership was formed in the business matchmaking rounds the company promoted to connect San Juan and national companies.
In January, Vicuña also set contracting rules. It said it chose the companies advancing in the process after three months of analysis, based on financial solvency, safety and technical capability, and that contractors must submit specific plans to integrate local labor and services.
Vicuña has also awarded accommodation logistics. On Nov. 18, the company awarded three camps with 450 beds each, which must be ready during the first and second quarters of 2027. The company expects more than 470 direct jobs during the construction phase.
Separately, the Ministry of Economy approved, through Resolution 1154/2026, the $9,737,014,000 investment plan under Argentina's Large Investment Incentive Regime (RIGI), and the regulator upheld Vicuña’s priority on the 500 kV line that will supply Josemaría.
Minera Zlato Had Already Been Chosen by Vicuña
Minera Zlato is part of Grupo Dumandzic, headquartered in San Juan. On its website, the company presents itself as a service provider to mining companies, strong in logistics and heavy machinery for high-mountain work: bulk earthworks, road construction and maintenance, heap leach pads, tailings dams, lithium production ponds and civil works. It has been a member of the San Juan Mining Chamber since 1992.
On June 3, 2025, Vicuña announced that it had awarded Zlato the maintenance of the existing road between Angualasto and La Majadita, a 170-km stretch in Iglesia department. That process was open only to San Juan companies and drew six local bidders. The company then estimated about 100 direct and indirect workers over roughly 13 months, with grading, reinforced-concrete culverts, gabions and road widening. Vicuña presented it as an alternative road to the current access through Guandacol, in La Rioja province.
Chediack Brings Mining and Road Projects in Mendoza and San Juan
José J. Chediack is an Argentine company founded in 1948 that specializes in engineering, construction, procurement and commissioning of infrastructure projects, according to its website. Vicuña described it as "one of Argentina's leading infrastructure and construction companies." The company reports operating bases in Buenos Aires, Córdoba, Mendoza, Neuquén and Uruguay.
Among its mining projects, the company lists Barrick's Pascua Lama project in San Juan; La Alumbrera, in Catamarca; and a lithium processing plant for Arcadium Lithium, also in Catamarca. Its awards include road project of the year for the Paso Pehuenche corridor on National Route 145 in Mendoza and for section III of the Ischigualasto–RN 40 and RN 150 junction stretch in San Juan, as well as a special mention for the snow sheds on National Route 7 between Uspallata and the Chilean border.