Argentina LNG to Invest $14.7 Billion in Two Years, With First LNG Unit Due to Start Up on June 30, 2030

Ministry of Economy Resolution 2027/2026 formalized the entry into the RIGI of the YPF, Eni and XRG project as a Strategic Long-Term Export Project. It splits the $50.75 billion into two stages, sets Dec. 31, 2028, as the deadline to meet the minimum investment and extends tax and foreign-exchange stability to 2061

by Lucía Martínez

According to the resolution, the project will be executed in two stages

The investment plan that Argentina's Ministry of Economy approved for Argentina LNG calls for $6.397 billion in qualifying assets in the first year and $8.29 billion in the second, counted from notification of the measure: $14.687 billion over two years.

The figures are set out in Resolution 2027/2026, signed by Economy Minister Luis Caputo and published in Argentina's Official Gazette, which formalizes the entry into Argentina's Large Investment Incentive Regime (RIGI) of the project developed by YPF, Argentina's state-controlled oil and gas company, with Eni, the Italian energy company, and XRG, ADNOC's international investment arm, as a Strategic Long-Term Export Project (PEELP).

The resolution turns the Evaluation Committee's recommendation into an administrative act and sets Nov. 19 as the adhesion date, when the applicants completed the additional information that Argentina's Secretariat of Energy had requested. With that signature, the process that Horacio Marín, YPF's chairman and CEO, had described as a necessary condition for signing the final investment decision (FID) is now complete.

First Floating Unit to Enter Operation on June 30, 2030

According to the resolution, the project will be executed in two stages. The first runs from July 2024 to 2030 and carries a projected investment of $26.377 billion for detailed engineering, procurement and construction of the floating liquefaction units, plants and pipelines, the plants of the Neuquén Industrial Complex, and up to 200 wells for the ramp-up. Start-up is estimated for June 30, 2030, when the first floating LNG (FLNG) unit enters commercial operation.

The second stage runs from 2031 to 2050 and totals $24.372 billion, allocated to upstream development over the life of the project and to maintenance of the facilities. Its start-up is scheduled for June 30, 2031, with the second unit in commercial operation. Each stage on its own exceeds the $1 billion floor that the regulations require of PEELP projects. Together they make up the $50.75 billion declared, $250 million less than the $51 billion YPF reported when the consortium filed its application on Aug. 13.

The measure sets Dec. 31, 2028, as the deadline to reach the category's minimum investment of $2 billion. It also requires the two project vehicles to show jointly that, in each of the first two years, they invested at least 20% of that minimum. The amounts declared for that period clear the threshold comfortably.

YPF chairman and CEO Horacio Marín during the interview conducted by Shale24 director Julián Guarino

Tax and Foreign-Exchange Stability

Article 5 grants tax, customs, foreign-exchange and regulatory stability for 30 years from the start-up of each stage: until June 30, 2060, for the first and until June 30, 2061, for the second. Law 27,742, the Bases Law that created the RIGI, allows that extension for strategic export projects executed in successive stages, provided the first stage meets the minimum investment commitments. The Secretariat of Energy considered it appropriate given the size of the project, its schedule and the amounts for each stage.

The holders are two Single Project Vehicles, MIDCO ARLNG I SA and UPCO ARLNG I SA, which were previously single-shareholder corporations. The first holds the floating units, the plants and the pipelines. Both signed a joint and several liability commitment covering the regime's obligations.

The applicants submitted a supplier development plan under which about 45% of goods and works will be provided by local suppliers, more than double the 20% required by the rules. The resolution also approves the list of goods each vehicle may import duty-free and accepts the arbitration clause they proposed, which Argentina's Treasury Attorney's Office found to be consistent with the law. The Central Bank raised no objections on foreign-exchange matters.

 

Plan Calls for 1,416 Wells and $9 Billion in Annual Exports

The project description includes drilling, fracturing and completing about 1,416 horizontal wells in the Meseta Buena Esperanza I and II, Las Tacanas I and II and Aguada Villanueva Norte blocks in Vaca Muerta, one of the world's largest shale plays, in Argentina's Neuquén Basin. The gas will be treated at the Neuquén Industrial Complex and carried through a dedicated 48-inch gas pipeline and a 24-inch multiproduct pipeline, each 524 kilometers long, to the Río Negro Industrial Complex near the Golfo San Matías. There, ethane, propane, butane and natural gasoline will be separated and fractionated, and condensate will be stabilized. The two FLNG units, with capacity of 6 million tonnes per annum (MTPA) each, will operate in the gulf.

Export revenue is estimated at about $9 billion a year from 2033. All output will go to export markets, except for transitory and marginal volumes. Projected employment is 20,000 jobs a year during construction, with peaks of 40,000, and 8,000 during operations.

For YPF, Argentina LNG is the largest by investment amount among the seven projects the company has in the RIGI. YPF’s board unanimously approved the FID, and the three partners are scheduled to sign it on Monday, Nov. 30, at the Palacio Libertad in Buenos Aires.